CONSTRUCT NEW PARKING STRUCTURE · 2025-08-19
1. The southwest driveway and part of the south drive were moved south because of the addition of a yard south of blding S1. Requiring to also change the water, sewer and storm lines in that area.
2. A water line connecting to building S1 and the pavilion has been provided.
3. A Sewer line for the pavilion has been added.
4. A motorized sliding gate was added southwest of bldg. S1 on the south-north fire lane entrance.
5. A new fence has been added south of the volleyball and basketball c · 2025-02-11
Project is part of the ASU Research Park ("ASURP") master development plan. Phase 1 consist of the development of 134,000 sf main building and 3 1/2 levels parking garage. Utility and drainage infrastructure are proposed to serve both phase-1 and future phases · 2025-02-11
1. The southwest driveway and part of the south drive were moved south because of the addition of a yard south of blding S1. Requiring to also change the water, sewer and storm lines in that area.
2. A water line connecting to building S1 and the pavilion has been provided.
3. A Sewer line for the pavilion has been added.
4. A motorized sliding gate was added southwest of bldg. S1 on the south-north fire lane entrance.
5. A new fence has been added south of the volleyball and basketball c · 2025-02-11
Drainage changes under Revision 4 RAE240010. · 2025-02-11
Project is part of the ASU Research Park ("ASURP") master development plan. Phase 1 consist of the development of 134,000 sf main building and 3 1/2 levels parking garage. Utility and drainage infrastructure are proposed to serve both phase-1 and future phases · 2025-02-11
Project is part of the ASU Research Park ("ASURP") master development plan. Phase 1 consist of the development of 134,000 sf main building and 3 1/2 levels parking garage. Utility and drainage infrastructure are proposed to serve both phase-1 and future phases · 2025-02-11
1. The southwest driveway and part of the south drive were moved south because of the addition of a yard south of blding S1. Requiring to also change the water, sewer and storm lines in that area.
2. A water line connecting to building S1 and the pavilion has been provided.
3. A Sewer line for the pavilion has been added.
4. A motorized sliding gate was added southwest of bldg. S1 on the south-north fire lane entrance.
5. A new fence has been added south of the volleyball and basketball c · 2025-02-11
Project is part of the ASU Research Park ("ASURP") master development plan. Phase 1 consist of the development of 134,000 sf main building and 3 1/2 levels parking garage. Utility and drainage infrastructure are proposed to serve both phase-1 and future phases · 2025-02-11
Project is part of the ASU Research Park ("ASURP") master development plan. Phase 1 consist of the development of 134,000 sf main building and 3 1/2 levels parking garage. Utility and drainage infrastructure are proposed to serve both phase-1 and future phases · 2025-02-11
Revision for Underground Fire Permit · 2025-02-11
4th Engineering Revision to the ASU research park project that is associated with: DS220920, and EN220060. The latest revision was approved through: RAE240010. · 2025-02-11
Project is part of the ASU Research Park ("ASURP") master development plan. Phase 1 consist of the development of 134,000 sf main building and 3 1/2 levels parking garage. Utility and drainage infrastructure are proposed to serve both phase-1 and future phases · 2025-02-11
1. The southwest driveway and part of the south drive were moved south because of the addition of a yard south of blding S1. Requiring to also change the water, sewer and storm lines in that area.
2. A water line connecting to building S1 and the pavilion has been provided.
3. A Sewer line for the pavilion has been added.
4. A motorized sliding gate was added southwest of bldg. S1 on the south-north fire lane entrance.
5. A new fence has been added south of the volleyball and basketball c · 2025-02-11
The antenna yard, South of building S1 has been reduced in size, grading has been updated accordingly. · 2025-02-11
3rd Engineering Revision to the ASU research park project that is associated with: DS220920, and EN220060. · 2025-02-11
At Risk Grading · 2023-07-28