CONSTRUCT NEW TWO (2) STORY PARKING GARAGE - 794 spaces · 2024-09-04
A proposed office site, including 2 multi-story office buildings, 2 parking garages, and associated hardscape, parking, and utilities. · 2024-08-27
A proposed office site, including 2 multi-story office buildings, 2 parking garages, and associated hardscape, parking, and utilities. · 2024-08-27
Sewer Permit · 2024-08-27
Underground Fire Permit · 2024-08-27
A proposed office site, including 2 multi-story office buildings, 2 parking garages, and associated hardscape, parking, and utilities. · 2024-08-27
Proposed interim revisions to the public waterline to coordinate with construction of the Carvana Corporate Campus site. · 2024-08-27
A proposed office site, including 2 multi-story office buildings, 2 parking garages, and associated hardscape, parking, and utilities. · 2024-08-27
A proposed office site, including 2 multi-story office buildings, 2 parking garages, and associated hardscape, parking, and utilities. · 2024-08-27
A proposed office site, including 2 multi-story office buildings, 2 parking garages, and associated hardscape, parking, and utilities. · 2024-08-27
Revisions include redesigning potions of the site grading and storm drain design to align with the updated sited design. The removal of a proposed drywell based on results from a percolation test. Revision to the proposed public waterline realignment. The addition of water and sewer services to a site water feature. Revisions were made to sheets C1, 3, 7-9, 11, 12, 15, 19, 21 &23. · 2024-08-27
Delta 1 Revision submittal for the previously approved Carvana Corporate Campus project. · 2024-08-27
2nd Revision submittal for the Carvana Corporate Campus project. · 2024-08-27
Water Permit · 2024-08-27
Delta 1 Revision submittal for the previously approved Carvana Corporate Campus project. Sewer Permit · 2023-03-30
PHASED FOUNDATION SUBMITTAL · 2022-01-19
At-Risk Grading Permit for the Carvana Office Project · 2021-12-29