17010-10012-05023
Corrections Issued
Supp to revise height on inventory to match building plans only. Revise the height to 55 feet, as noted on the approved drawings.(44FT. SHOWN ON PLANS.) · 2026-09-03
INSTALLATION OF (5) RAINWATER CATCHMENT SYSTEMS. · 2026-08-25
ONSITE 1-1/2" & 2" IRRIGATION WATER SERVICE AND CONNECTION, (5) 1-1/2" BACKFLOW DEVICES, (4) PRIVATE METERS · 2026-08-21
Supplemental permit to 17010-10000-05023: Revised emergency exit route for a 76-unit, four-story apartment building currently under construction. This revision provides an alternate path of travel concrete sidewalk from the Ground Floor Units 105 and 106 to the north stair landing, exiting through the open-to-sky courtyard to the alley exit gate. The existing exit route through the lobby to Broadway will remain unchanged.The original egress path through the north side yard is not code-compliant · 2026-07-20
Fire alarm system for new apartment building. FACP, (4) remote power supplies, and (206) signaling line and notification appliance devices. · 2026-07-07
ePlanInstall Roof Mount Solar panels: 205 PV modules & 3 inverters. ( 112.75 kW DC / 102.31 kW AC ) · 2026-06-17
Installation of one new hydraulic elevator. · 2026-06-08
POTABLE WATER AND WASTE/ VENT. 3 INCH DOMESTIC WATER METER AND 3 INCH R.P. BACKFLOW PREVENTER. · 2026-05-29
REVISION TO PREVIOUSLY APPROVED PLAN. REVISED POTABLE WATER, WASTE & VENT SYSTEMS. ADDING RAINWATER AND GRAYWATER SYSTEMS. · 2026-05-29
Access Control · 2026-05-15
FULL PLAN CHECK FOR A NEW APARTMENT COMPLEX CONSIST OF 9 BUILDINGS (100% AFFORDABLE HOUSING). (1 FOUR FLOOR BUILDING AND EIGHT 2-STORY TOWN HOUSES). SCOPE INCLUDES NEW 4000A 120/208 SERVICE WITH 150KW EMERGENCY GENERATOR. TOTAL AFFECTED AREA IS 54,861SQ.FTPER BUILDING PERMIT #17010-10000-05023 FOR THE 4-STORYPROPOSED 76-UNIT, 4 STORY, TYPE VA OVER TYPE IA APARTMENT/GARAGE.TRANSIT ORIENTED COMMUNITIES 100% AFFORDABLEWORK FORCE TIER 3 AND TIER 4, 3 · 2026-05-15
Installing (2) Hot Water Boilers and (1) Hot Water Storage Tank · 2026-05-14
AOR 2-way communication · 2026-05-09
GAS OUTLETS, EARTHQUAKE VALVE, RAIN WATER DRAINS AND WATER HEATERS · 2026-05-06
New ERRCS Installation · 2026-04-29
Adding devices for telephone and communication outlets. New telephone and computer wiring- voice and data. · 2026-04-29
[EPLAN] CHANGES TO APPROVED SET AND PERMIT UNDER 20041-10001-10467. CHANGE OF ENGINEER OF RECORD FROM E17831 TO E18883. CHANGES MADE TO LIGHT FIXTURE SCHEDULE, T24 SHEETS, LIGHTING FLOOR PLAN, POWER FLOOR PLAN, PANEL SCHEDULES, AND SINGLE LINE DIAGRAM · 2026-04-28
[ePlan] Changes to approved plans. Revised conductors to AL, updated fault current calculations and voltage drop calculations, updated AIC ratings, revised power and lighting floor plans. Clouded changes only. Narrative attached. · 2026-04-28
(Eplan) Revision to approved plans. Electrical updates made to sheets E1.02, E2.02, E2.15, & E3.08. The was primarily to alternate normal and emergency facade and hallway lighting. Remove the fuses for some condensing units and adding a mini-inverter for emergency lighting at the recreational room. · 2026-03-17
(EPlan) Installation of 114.95 kW DC/103.77 kW AC PV system includes 209 modules with 59 microinverters and 1 combiner box connected to existing main service panel. · 2026-03-11
Plan check for underground fire protection and fire hydrant system. · 2026-02-20
Install new underground fire lines for two buildings ( apartment and townhouse buildings). 6" fire service and 6" DC backflow device and 4" fire service with 4" DC backflow device. · 2026-02-20
[E-Plan] Plan Check Only. Full plan check for PV2 system due to changes that exceeds 50% of the system's initial design. Permit fees are paid under the master permit. Revision to Approved Plans: We changed the brand of inverter due to availability. See PV3.2We are mounting the inverter on the back of the pipe rack.The site images have been inverted 180 degrees and the obstructions have been labeled. · 2025-12-17
20041-10002-10467
Corrections Issued
Supplemental to approved plans. Full plan check energy and power, includes new power devices, new circuits, and new lighting fixture controls.Original work description:FULL PLAN CHECK FOR A NEW APARTMENT COMPLEX CONSIST OF 9 BUILDINGS (100% AFFORDABLE HOUSING). (1 FOUR FLOOR BUILDING AND EIGHT 2-STORY TOWN HOUSES). SCOPE INCLUDES NEW 4000A 120/208 SERVICE WITH 150KW EMERGENCY GENERATOR. TOTAL AFFECTED AREA IS 54,861SQ.FT · 2025-09-11
PLAN CHECK ONLY. PERMIT UNDER 20042-10000-06280. REVISISON TO 20042-10001-06280 TO REVISE STORM DRAIN SYSTEM ONLY. · 2025-07-31