26041-10000-36194
Corrections Issued
(EPlan) Fire alarm plan check. Scope of work includes 1 FA control panel, 2 communication devices and 9 FA devices. · 2026-09-10
INSTALL (2) INTERNALLY ILLUMINATED WALL SIGNS. ( 3'-0" X 7'-6" ) · 2026-09-02
(EPlan) Changes to an approved set clouded changes only, adjusted PV roof layout and conductor sizing changed.PV arrays on the roof have been realigned due to roof objects being installed on the roofprior to our roof survey being completed. The equipment rack on the roof for the inverter, PV panel boardand DAS has been relocated to accommodate the revised array layout. The available fault current values wererevised on the SLD. All equipment KAIC values are still valid.Electrical Sheets have been · 2026-08-31
Rainwater catchment system with two duplex sump pump systems. · 2026-08-20
[ePlan] NEW TRASH ENCLOSURE , ALL WORK PER ENGINEERING · 2026-07-24
24010-20006-01298
Quality Review Completed
Eplan Supplemental to 24010-20000-01298 to Add locker room underneath interior staircase, all work per engineering · 2026-07-15
revision to previously approved set of plans. · 2026-07-01
26020-20000-01278
Submitted for Quality Review
EPLAN New 4 ft high retaining wall x ? ft high , all work per engineering · 2026-06-17
24030-20001-02338
Submitted for Quality Review
eplan Supplemental to 24030-20000-02338 to revise grading and Lid plans · 2026-06-17
Emergency Responder Radio Coverge System for new Construction. · 2026-06-08
(6) RAIN WATER DRAINS. · 2026-05-20
[E-Plan] New PV2 roof mounted commercial solar system consisting of 150 modules, 150 optimizers and 1 central inverter. System size is 82.5 kWDC/80kWAC · 2026-05-12
REVISIONS TO APPROVED PLANS: RELOCATED RISER FOR SYSTEM 1 (CHANGES ARE CLOUDED UNDER DELTA 5).PLAN CHECK ONLY. · 2026-04-23
Revisions to approved plan: Relocate on-site fire hydrant and FDC locations.Plan check only. · 2026-04-16
[E-Plan] Delta 11 clouded changes only. Supplemental permit to add restroom, changes to single line diagram and T-24 sheets, changes to service equipment layout... · 2026-01-26
FIRE HYDRANTS AND FIRE SPRINKLER SYSTEMS FOR COMMERCIAL BUILDING. 10" FIRE METER. 10" BACKFLOW DEVICE. · 2025-11-14
Supplemental permit to add restroom. Work includes potable water and waste/vent. · 2025-10-16
VENTILATION FOR THE REMOTE RESTROOM (SHEET M-2.0, DETAIL 3). · 2025-10-16
[E-PLAN] DELTA "9" SUPPLEMENTAL CHANGES TO AN APPROVED SET. REVISIONS INCLUDE CHANGES TO SLD, EQUIPMENT LAYOUT, ELEVATION DIAGRAM, NOTES AND PANEL SCHEDULES.**Owner's information is missing** · 2025-09-12
POTABLE WATER AND WASTE/VENT. 2" DOMESTIC METER WITH BACKFLOW PREVENTER. · 2025-08-22
HVAC COMMERCIAL BUILDING. · 2025-08-22
[ePlanLA] Plan check for power and energy, 3,000A, 277/480V, 3 ph, 4W, Service, 5 transformers, 10 sub-panels, New warehouse and office. Total lighting area: 77,972 sq ft. · 2025-08-22