26016-10000-20129
Quality Review Completed
MODIFICATIONS TO EXISTING GORILLA HABITAT AT THE ZOO THAT CONSIST OF A SECONDARY TRANSFER CHUTE. PROPOSEDSECONDARY CHUTE TO BE INSTALLED TO BE CONSTRUCTED OF HOT-ROLLED STEEL AND OPEN WIRE MESH TO MATCH EXISTING CONDITIONS. · 2026-08-31
REMOVE (E) DAMAGED RETAINING WALLS AND REPLACE WITH (N) PIPE & BOARD RETAINING WALLS. CUT=55CY , FILL=45CY2 OF 226030 - 10000 - 04223 · 2026-08-19
26030-10000-04223
PC Info Complete
REMOVE (E) DAMAGED RETAINING WALLS AND REPLACE WITH (N) PIPE & BOARD RETAINING WALLS. CUT=55CY , FILL=45CY1 OF 2see 26020 - 10000 - 01391 · 2026-08-11
Replace corroded electrical. add (4) receptcels · 2026-06-01
**EPLAN** 2 of 3**** LA ZOO - HOLDING BUILDING- CONSTRUCT NEW ROOF EXTENSIONS. INSTALL NEW WIND BARRIER (RETRACTABLE TARP) AT THE HOLDING DENS. INSTALL NEW GATE AT THE ANIMAL TRANSFER CHUTE. REPLACE EXISTING GUILLOTINE DOORS WITH NEW. STRUCTURAL UPGRADES AS REQUIRED FOR NEW WORK · 2026-05-14
**EPLAN** 3 of 3**** LA ZOO - STEEL SUPPORT COLUMNS & NETTING FOR ANIMAL ENCLOSURE - REPLACE THE EXISTING CABLE SUPPORTED MESH/NETTING ENCLOSURE SYSTEM · 2026-05-12
Supplemental permit to 25041-10000-51081 to change work description to : Install new 12KVA transformer. Install new 400 amp panel. Install 10 level 2 EV chargers. · 2026-05-06
(Eplan) General Electrical scope for alternation project by replacing the existing electrical panels with new panels and adding power for some fans · 2025-11-25