New 6-story, 22-unit (2 ELI + 2 VLI + 1 LI = 22%) affordable housing apartment (factory-built housing) with 5 levels of Type IIB over 1-level Type IA lobby and parking at ground floor utilizing TOC Tier 3 incentives. · 2026-08-27
Hot water system inspection · 2026-04-22
***22% affordable housing apartment***Installation of (1) new hydraulic elevator · 2026-01-07
INSTALLATION OF NEW HAVAC SYSTEM. INLCUDES ENVIRONMENTAL VENTILATION. · 2025-10-06
PLAN CHECK ONLY: REVISE RATED SPEED, PUMP, AND MOTOR. · 2025-10-01
INSTALLATION OF NFPA-13 SPRINKLER SYSTEM. INCLUDES UNDERGROUND, SPRINKLERS, AND STANDPIPE. 6" FIRE SERVICE METER. 6" BACKFLOW PREVENTION DEVICE. · 2025-09-22
NEW PLUMBING SYSTEM. WORK INCLUDES POTABLE WATER AND WASTE/VENT. 4-INCH DOMESTIC WATER METER WITH 4-INCH RP BACKFLOW PREVENTER. · 2025-09-19
Changes to approved plans. Added HVAC equipment, updated feeder schedule, updated load calculations.**PC for clouded delta B changes only. · 2025-09-11
(Eplan) Change of the main breaker at switchgear from 1200 Amps to 1000 Amps (per Inspector's request)Update to the lighting fixtures & Revised circuitry for emergency lightingNew location of emergency generator which serves only the elevatorRefer to attached narrative · 2025-09-11
[Eplan] Full Plan Check for power and energy for a 6 story apartment building. Electrical scope of work8 includes new 1200A, 120/208V, 3ph service with 22 unit panels, circuits andnew lighting. Total energy sq. ft. 11227 indoor and 200 outdoor. . · 2025-09-11
22042-20003-17131
PC Info Complete
Revision to include medium pressure gas system and change water heater from tank to tankless. See application comment. · 2025-08-12
22042-10001-17131
Corrections Issued
REVISION TO PREVIOUSLY APPROVED PLANS. REVISE WASTE/VENT SYSTEM AND ADDITION OF RAINWATER. · 2025-08-04
[ePlanLA] Install Fire Alarm System, 1 FACP with 105 Fire Alarm Devices INSTALLATION OF NEW FIRE ALARM SYSTEM FOR NEW 6 STORY 22 UNIT APARTMENT BUILDING · 2025-07-09