26041-10000-30363
PC Info Complete
[E-Plan] PV1 ADDITION OF 11.610 KW DC / 11.500 KW AC / 10.714 KW CEC-AC ON EXISTING INVERTER WITH EXISTING 13.50 KWH BATTERY BACKUP - ROOF MOUNT · 2026-09-02
(EPlan) Plan check for installation of energy storage system. Scope of work includes 1 energy storage systems and 1 load center connected to existing main service panel. · 2026-02-23
(EPlan) Plan check only, no new equipment just relocation. PLEASE EXPEDITE. ATTN: EDWIN LIZARRAGARevision: 1. Powerwall and AC disconnect relocated from interior garage wall to exterior East wall under existing deck. 2. Electrical load calculations updated to match site conditions. 3. Gateway feeder breaker in main panel changed from 90A/2P to 125A/2P. · 2025-12-27