REPLACEMENT OF (6) EXISTING EXTERIOR BI-PARTING SLIDING AUTOMATIC DOORS, SIDELIGHTS + TRANSOMS (WHERE OCCURS) AT TERMINAL 2. · 2026-09-10
26016-10000-22127
Quality Review Completed
T2 BAGGAGE CONVEYOR REMOVAL PROJECT, AS PART OF THE LAX TERMINAL AND DEPARTURE REFRESH PROGRAM, INCLUDES THE FOLLOWING SCOPE ITEMS:- DEMOLITION OF CURBSIDE BAGGAGE CONVEYOR AND HOUSING AT TERMINAL 2; INFILL OF SLAB OPENING; REPAIR ADJACENT CONCRETE FOR FLUSH WALKING SURFACE; INFILL OF A PLASTER FINISH WALL; DEMOLITION OF SOFFIT AT ARRIVAL LEVEL AND REPLACEMENT WITH INFILL WALL AND SMALLER SOFFIT. · 2026-09-02
**ePlan**LAX**Early Start - Interior Demolition of Walls, Ceilings and Finishes inside Terminal 2 Sky Club Space. · 2026-08-27
NEW LIGHTING AT LAWA: TERMINALS 1 THROUGH TERMINAL 7 AND AT TBIT. ARRIVALS ; GARAGE CORE ELEVATORS ; DEPARTURE ; THEME BUILDING CANOPY 480566 SFT AND FACADE 108576 SFT PLAN · 2026-08-11
Supplemental to Permit #25016-10001-17795 At Level 1, existing Electrical Room T2-1-2A-ER100, keep unchanged existing wall ratings of 1 hour and nonrated per LADBS Permit #18016-10000-19522 · 2026-08-05
REPLACE WATER HEATER · 2026-07-24
Furnish and install conduit and low voltage cable for ERRCS · 2026-05-11
Low Voltage Electrical Installation for Building Automation System · 2026-04-29
Plan check for fire sprinkler system. · 2026-04-23
REPLACE WATER HEATER · 2026-04-17
Make changes to the previously approved plan. Plan check only. Permit fees paid under 25043-10000-05122. · 2025-12-18
Phase 3A - Terminal 2 Final Renovation -Plan check heating, venting, and air conditioning. · 2025-12-17
Plan check for fire sprinkler system. · 2025-11-17
TENANT IMPROVEMENT. NFPA 13. ADDITION OF HEADS · 2025-11-03
Plan check for heating, venting and air conditioning. · 2025-10-13
[ePlan]Supplemental to approved energy only set:Provide new dedicated outlets for new display video wall at departure level. · 2025-10-08
Make changes to the previously approved plan. Plan check only. Permit fees paid under 25044-10000-07680. · 2025-08-28
LAWA-LAMP Project Installation of new domestic water site piping along World Way north and south with connections to existing domestic water plumbing in terminals 4, 5, 6, 7 and 8. Domestic water connections to terminals will replace existing domestic water connection. · 2025-08-27
25041-10000-26103
PC Info Complete
[ePlan] Commercial space TI. New lighting, controls, receptacles. Total affected area is 2424 sqft. Plan check for energy. · 2025-08-26
Make changes to the previously approved plan. Plan check only. Permit fees paid under 21042-10000-85656. · 2025-08-21