24044-10001-16574
Verifications in Progress
**** ASSIGN TOGETHER: M26LA15570, M26LA15581, M26LA15573, M26LA15575 (this app)**** **** OG PC: MATT, OG PC FOR RA APPROVAL (M22LA03980): MY ****REVISION TO PREVIOUSLY APPROVED PLANS UNDER #24044-10000-16574. INCLUDING UPDATED RATIONAL ANALYSIS, ADDED TRANSFER DUCTS, AND REVISED AIR DISTRIBUTION. **** See Inspector correction notice requiring rational analysis for all floors. This required that the mechanical distribution plans be updated to fully match what is being installed based on site co · 2026-09-11
24016-10006-28040
Verifications in Progress
* Supplemental to 24016-10000-28040. Added new doors, frame and hardware. Updated 2hr rating wall line and added new doors along grid lines TC/T4. Added keynote 2.32 to extend wall rating at OA duct into mechanical room with shaft wall enclosure to allow for damper installation inside mechanical room side. · 2026-08-24
GENERAL HVAC TI IN BUILDING WITH EXISTING SMOKE CONTROL SYSTEM. SMOKE CONTROL SYSTEM APPROVED UNDER PERMITS 22044-10001-10742 AND 24044-10000-14047. · 2025-08-28
[Eplan] Revision to TI plans. Plan check for clouded changes. · 2025-08-19
FIRE SPRINKLER TI. ADDITION AND RELOCATION OF HEADS. · 2025-04-16
[ePlanLA] First Time Tenant, Existing 1200A, 4160V Medium Voltage, 8 Transformers(225KVA), 8 distribution(800A) 40 Sub-panels, New office tenant improvement electrical design in new core/shell space on level 13 to level 20 with approximate area of 142,566SF. New branch circuiting and lighting controls throughout the space. 37 story building. · 2025-04-04
Plan check for potable water and waste/vent systems. · 2025-04-03