eplan New 5-story with roof parking, Type IB, auto dealership with vehicle sales, repairs, parts and tire storage, circulation ramps, parking, and office use. project scope includes car wash. outdoor vehicle display, new driveways, site grading, and new landscape. · 2026-09-11
General HVAC revisions. · 2026-08-27
SUPPLEMENTAL PERMIT TO 26041-20000-02779 TO CHANGE THE WORK DESCRIPTION TO ADD ADDITIONAL ITEMS, 111 COMMUNICATION DEVICES AND REMOVE 4 OF THE 5 COMMUNICATION PANELS FOR A TOTAL OF 1. · 2026-08-25
Low Voltage security camera installation · 2026-08-25
Installation of 1 new cabled electric elevator. · 2026-06-04
New HVAC SYSTEM FOR A NEW AUTO DEALERSHIP (B, S1 & S2 OCCUPANCIES). SEE APPLICATION COMMENTS. · 2026-03-12
(E-PLAN)FULL POWER PLAN CHECK FOR A 4000A, 480/277V, 3-PH, 4W SYSTEM (AUTOMOTIVE DEALERSHIP). SCOPE OF WORK INCLUDES MAIN SWITCHBOARD, PANELS, TRANSFORMERS, MOTORS, EV CHARGERS, CIRCUITS, LIGHTING, AND CONTROLS.TOTAL AFFECTED AREA: 302,481 SQ FT · 2026-03-11
Installation of one new traction elevator. · 2026-03-10
(Eplan) Install a new rescue assistance communication System (1) Control Panel (8) Communication Devices. Note: Plan Check per applicant request. · 2026-03-04
REVISIONS TO APPROVED PLANS-DELTA 9ATTACHED TO THE SET OF PLANS IS A LIST OF THE CHANGES WHICH ARE LOUDED ON THE PLANS.FULL POWER PLAN CHECK FOR A 4000A, 480/277V, 3-PH, 4W SYSTEM (AUTOMOTIVE DEALERSHIP). SCOPE OF WORK INCLUDES MAIN SWITCHBOARD, PANELS, TRANSFORMERS, MOTORS, EV CHARGERS, CIRCUITS, LIGHTING, AND CONTROLS.TOTAL AFFECTED AREA: 302,481 SQ FT · 2026-03-03
(Eplan) Revisions to approved set. Change in pathway survivability from level 3 to level 0 because the system is to be monitored off-site (transmit off-premises) per NFPA 72 24.3.14.9.2. Also update wire type. We will need to expiate and we will also pay for the new plans to be stamp again. Attn Plan Checker: Dagim · 2026-03-03
Install Fire alarm devices for commercial building 192 FACP, Communication Device, andControl Panel. · 2026-02-23
REVISION TO APPROVED PLANS: ADDING PLUMBING FIXTURES (CHANGES UNDER DELTA 6). · 2026-02-10
Install new plumbing system including potable water, waste and vent, and storm drainage systems. 2" water meter. · 2026-02-10
LEVEL I METHANE MITIGATION SYSTEM. · 2026-01-30
NEW FIRE SPRINKLER SYSTEM, WITH STAND PIPE AND UNDERGROUND LINE. 8" FIRE SERVICE METER AND 8" DOUBLE CHECK DETECTOR ASSEMBLY BACKFLOW DEVICE. · 2026-01-27
Delta 8 revisions to approved plansAttached to the plans is a list of changes which are clouded on the plans(E-PLAN)FULL POWER PLAN CHECK FOR A 4000A, 480/277V, 3-PH, 4W SYSTEM (AUTOMOTIVE DEALERSHIP). SCOPE OF WORK INCLUDES MAIN SWITCHBOARD, PANELS, TRANSFORMERS, MOTORS, EV CHARGERS, CIRCUITS, LIGHTING, AND CONTROLS.TOTAL AFFECTED AREA: 302,481 SQ FT · 2025-11-25
DELTA 7 CHANGES TO APPROVED SET OF PLANS.A list of the narrative of the changes are attached to each set of revised plans.PLAN CHECK ONLY(((((((((E-PLAN)FULL POWER PLAN CHECK FOR A 4000A, 480/277V, 3-PH, 4W SYSTEM (AUTOMOTIVE DEALERSHIP). SCOPE OF WORK INCLUDES MAIN SWITCHBOARD, PANELS, TRANSFORMERS, MOTORS, EV CHARGERS, CIRCUITS, LIGHTING, AND CONTROLS.TOTAL AFFECTED AREA: 302,481 SQ FT · 2025-11-06
PLAN CHECK ONLY. CHANGE TO SPRINKLER HEAD MODEL. · 2025-10-16
22041-10003-45348
PC Info Complete
(E-PLAN)DELTA 6 REVISIONS- NEW CKTS, A PANEL FOR EV CHARGERS A narrative of all changes are stapled to the planssFULL POWER PLAN CHECK FOR A 4000A, 480/277V, 3-PH, 4W SYSTEM (AUTOMOTIVE DEALERSHIP). SCOPE OF WORK INCLUDES MAIN SWITCHBOARD, PANELS, TRANSFORMERS, MOTORS, EV CHARGERS, CIRCUITS, LIGHTING, AND CONTROLS.TOTAL AFFECTED AREA: 302,481 SQ FT · 2025-08-19
Plan check only. General HVAC revisions. · 2025-07-16
Plan check for clouded changes. Plan check Only. · 2025-06-02
Plan revision Delta 5 As-Built. · 2025-05-19