Change of use from Rec Room to ADU, with no sprinkler heads added or relocated. · 2026-08-11
Installation of 44 Level 2 EV Charging Stations. · 2026-07-16
Installation of new electrical service meter. · 2026-07-16
611'-0" LONG WITH MAX. 23'-0" IN HEIGHT TEMPORARY SHORING WITH LAGGING & SOLDIER PILES FOR NEW 5 STORY 58 UNIT MULTI FAMILY BUILDING OVER ONE LEVEL SUBTERRANEAN PARKING GARAGE · 2026-06-16
NEW 326.05' LENGTH AND 8.56' MAX HEIGHT RETAINING WALL - PER ENGINEER · 2026-06-16
NEW 5 STORY 58 UNIT APARTMENT BUILDING - ( 4 LEVELS OF RESIDENTIAL TYPE III - A ,OVER GROUND LEVEL TYPE I-A PARKING GARAGE & REC.ROOM & GYM & LOBBY & ONE RESIDENTIAL UNIT & OVER ONE LEVEL TYPE I -A SUBTERRANEAN PARKING GARAGE).��(TOC-TIER#3 PROJECT WITH 6 UNITS SET ASIDE FOR Extremely Low Income units. ) · 2026-06-16
*Eplan* Supplemental to permit # 19010-10000-06486 "To install tie-back anchorage sysytem on the roof ,intended for maintenance of building facades. · 2026-06-15
SUPPLEMENTAL TO PERMIT # 19010-10000-06486 TO REVISE THE PLANS : TO MAKE THE ELEVATOR SHAFT LARGER TO ACCOMODATE 2 ELEVATOR CABS &CONVERT 1 UNIT AT THE GROUND LEVEL TO REC. ROOM & CONVERT THE BICYCLE ROOM TO THR GYM & CONVERT OFFICE & PORTION OF ELECTRICAL ROOM TO THE LONG TERM BICYCLE ROOM & & INSTALL DEMISING WALLS AT GROUND LEVEK GYM TO CONVERT TO 4 REC. ROOMS & CHANGE FLOOR PLANS OF UNITS 211,311,411,511 & 413-511 & 213-413 & CONVER 2 STORY UNIT#213 IN TO 2 UNITS # 213 & 313 & · 2026-06-15
[EPLAN] CHANGE TO APPROVED SET UNDER 21041-10001-17980. PLAN CHECK FOR POWER ONLY. CONVERT REC ROOMS INTO 9 ACCESSORY DWELLING UNITS (ADUS) LOCATED AT THE 1ST & 2ND FLOOR. PROVIDE NEW 400A, 120/208V, 3PH, 4WIRE METER SECTION.BUILDING PERMIT: 25016-10000-04592 (B24LA38670) · 2026-06-08
In an existing apartment building, converting proposed ADUs TO RECOREATIONAL ROOMS. · 2026-06-08
GENERAL HVAC WITH GARAGE VENTILATION · 2026-06-03
REVISIONS INCLUDE ADDING SPLIT SYSTEMS & ENVIRONMENTAL EXHAUST. PREVOUSLY APPROVED PLAN UNDER 21044-10000-21230. · 2026-06-03
Witness Test for Ventilating System · 2026-06-03
200amp temporary power pole · 2026-06-01
Low voltage permit for 5 floors · 2026-06-01
WIRING AND INSTALLATION OF A NEW DAS SYSTEM WITH 1 DONNER ANTENNA AND 6 AREA ANTENNAS · 2026-06-01
[ePlanLA] Plan check for INSTALLATION OF A NEW FIRE ALARM SYSTEM, 266 Fire alarm devices and 1 FACP · 2026-06-01
Emergency Responder Radio Coverage System (ERRCS) (7) Antennas, (1) Communication System, (1) Bi-Directional Amplifier and (1) Battery · 2026-06-01
Plan check for Power and energy for a 2000 A Service120/208 Volts supply 60 Electrical Meters, Methane Zone, 70 sub-panels. Total lighting area: 44705sq ft. B#19010-10000-06486****Building Work description******NEW 5 STORY 58 UNIT MULTI FAMILY BUILDING · 2026-05-14
POTABLE WATER, WASTE/VENT WITH SEWAGE EJECTOR, MEDIUM PRESSURE GAS AND STORM DRAINAGE WITH SUMP PUMP. 4" WATER METER, 4" BACKFLOW PREVENTER. · 2026-04-30
Methane mitigation Level II. · 2026-04-30
ADDED INDIVIDUAL WATER HEATERS FOR EACH UNIT (PREVIOUSLY APPROVED AS A CENTRAL WATER HEATING SYSEM). REVISED WATER CALCULATIONS AND RISER DIAGRAMS. · 2026-04-30
NEW PLUMBING - POTABLE WATER, WASTE/VENT AND LOW PRESSURE GAS. 4-INCH DOMESTIC WATER METER WITH RP BACKFLOW PREVENTER. · 2026-04-30
Install new fire sprinkler and standpipe systems. 4" fire service and 4" DC backflow device. · 2026-03-31
INSTALLATION OF HYDRAULIC ELEVATOR. · 2026-03-26