*EPLAN* Email 09/02/26 (Attn: Farshad Alimohamadi /Scrn: daniel Chan) Infiltration Galleries deferred submittal for storm prisms. Non-Bldg Permit # 22026-10000-00253 · 2026-09-10
Supplemental permit 26020-20000-01331 shoring plan is limited to the Pile & Tieback schedule on sheet SS600. Tiebacks # 1 - 60, #159-252 have been revised from strand to the equivalent rod size, provided by the shoring designer. · 2026-09-01
Shoring design for Construction of underground infiltration galleries and diverting stormwater Grading Permit under 22030-10000-04536 · 2026-08-03
DESIGN & CONSTRUCTION OF INFILTRATION GALLERIES BENEATH DMG PARK · 2026-06-08
GRADING FOR NEW INFILTRATION SYSTEMS · 2026-06-08
Expedited - [EPLAN] PLAN CEHCK FOR POWER ONLY , SCOPE OF WORK INCLUDES A NEW 400A SERVICE (277/480 3P, 4W) FEEDING A NEW 400A SWITCHBOARD THAT IS INSTALLED IN A CLASSIFIED HAZARDOUS AREA, SWITCHBOARD FEEDS VARIOUS MOTOR EQUIPMENT, A NEW EV PANEL AND OTHER RELATED HOUSE EQUIPMENT. · 2026-06-02
22026-20001-00253
Verifications in Progress
Attn: Farshad/ Charles BOE projectDesign and Construction of Infiltration Galleries underneath DMG Park. Original permit application submitted by paper plan check under application number 22026-10000-00253 Plans have been updated to comply with LABC 2026. · 2026-06-01
[ePlan] Plan check only revisions to update scope and current code cycle notes- Sheet EG01 only*** Applicant work description below: *** Attn: Francis Ysaguirre. Supplemental plan check for revisions to comply with latest building code.Design and Construction of Infiltration Galleries underneath DMG Park. Plans have been updated to comply with LABC 2026. We would like to request an expedited review, as the contract has already been awarded and the NTP has been issued for the contractor to begin · 2026-05-02