[eplan] Power plan check for digital message displays. Scope of works, new 500kVA XFRM, new 1600A distribution board, new distribution panels for digital message displays**Applicant notes, **LAX PROJECT** **EXPEDITED REVIEW REQUESTED** PROVIDE POWER FOR NEW ATCT DIGITAL SCREEN ON FOUR SIDES OF THE EXISTING CONTROL TOWER ON ALL LEVELS. · 2026-09-09
Install electrical disconnects and connect existing/provided S.O. cord to the electrical control panel for the Passenger Boarding Bridge (PBB). Terminate electrical conductors to breakers within the control panel. Torquing and power release. · 2026-09-04
26016-10000-21648
Quality Review Completed
**ePlan**LAX**CHANGE OF USE FROM OFFICE BUILDING TO SIGN SUPPPORT STRUCTURE - PERMIT FOR (N) EXTERIOR DIGITAL MEDIA STRIP ON THE (E) UNOCCUPIED FORMER AIRPORT TRAFFIC CONTROL TOWER (ATCT) AND ASSOCIATED UTILITY CONNECTIONS/RELOCATIONS · 2026-09-02
LAX Structurally repair and patch the specific locations where material testing coupons were obtained from the exterior light-gauge outriggers. · 2026-07-21
Electrical alterations for Levels 1 and 2 FF&E relocations, including removal/relocation of existing devices, new receptacles, floor boxes, furniture power connections, branch circuits, conduit and wiring connected to existing panels. No new service or new equipment rated 600A or greater. · 2026-07-14
Relocating Sprinklers above a new exit lane in LAX Terminal 6 · 2026-07-13
cut and cap sewer and water lines · 2026-06-30
Adding electrical power & data · 2026-06-16
THE SCOPE OF WORK CONSISTS OF INSTALLING NEW FLUORO-K (FK-5-1-12) CLEAN AGENT SYSTEM AT LAX AIRFIELD 1 - REG. ROOM 102 W/VAULT (ZONE 1). AND EMERGENCY GENERATOR 101 (ZONE 2). THESE TWO ZONE WILL OPERATE INDEPENDENTLY OF ONE ANOTHER. THE FLUORO-K CLEAN AGENT PANEL SHALL BE KIDDE FIRE - ARIES MLX CONTROL PANEL. THE ROOM WILL BE PROTECTED WITH A MAIN SUPPLY OF FLUORO-K AND A CONNECTED RESERVE SUPPLY. · 2026-06-03
Retrofit of existing office space · 2026-05-22
Replace Governor Ropes.State #: 162615; 186034; 180595 · 2026-05-06
Detection and Controls for Flouro-K Suppression system · 2026-05-05
EPLAN. POWER PLAN CHECK FOR NEW PULON LOCATION FOR LAX. SOW INCLUDES 800A SERVICE, TRANSFORMERS AND CIRCUITS. LAX-ATMP ATTN FRANCIS YSAGUIRRE · 2026-05-04
CONNECT WATER FLEX LINES TO 8 WATER HOSE CABINETS AT LAX · 2026-04-22
Extend and Relocate an existing Standpipe with Hose Valves. Vertical Core Stair 02 VC P2A. Provide new sprinklers to existing sprinkler system. · 2026-04-22
25044-10000-11414
PC Info Complete
Plan check for heating, venting and air conditioning. · 2026-04-16
Relocate fire hydrant with its lateral and valve. · 2025-11-07
[ePlanLA] Plan check for new fire alarm system, fire alarm devices: 133 and 1 FACP, NEW FIRE ALARM SYSTEM · 2025-10-28
25044-10000-11219
PC Info Complete
Plan check for heating, venting, and air conditioning. · 2025-10-14
Plan chek for underground fire protection. · 2025-09-04