NEW INSTALLATION OF ONE(1) 4000LB CAPACITY, AND ONE(1) 3500LB CAPACITY, 12-FLOOR, 350FPM, PASSENGER ELEVATORS, PURSUANT TO THE SCOPE OF WORK PLANS SUBMITTED. · 2026-08-19
INSTALLATION OF (1) SINGLE TEMPORARY RACK & PINION PERSONNEL HOIST, 8000LBS CAPACITY @ 275FPM, 12 FLOORS, PURSUANT TO PLANS SUBMITTED AND SUBJECT TO CITY OF CHICAGO DEPT. OF BUILDINGS ELEVATOR BUREAU INSPECTION. · 2026-06-17
***HOIST PERMIT****INSTALLATION OF TEMPORARY SINGLE 8000LBS CONSTRUCTION HOIST · 2026-06-16
DDS / 2019 CBC: NEW CONSTRUCTION OF A 12-STORY RESIDENTIAL BUILDING (199 UNITS) W/ NO BASEMENT TO INCLUDE GROUND PARKING (42 AUTO PARKING SPACES + 199 BIKE PARKING SPACES) AND ASSOCIATED SITE WORK AS PER PLANS. (FOUNDATION / SUPERSTRUCTURE PERMIT: 100979631) (OCCUPANCY GROUP: R-2 / TYPE 1A CONSTRUCTION) CONSULTANT REVIEWER: GLOBETROTTERS ENGINEERING · 2026-03-25
100979631
PHASED PERMITTING
(DIRECT DEVELOPER SERVICES / 2019 CBC) FOUNDATION / SUPERSTRUCTURE PERMIT FOR THE NEW CONSTRUCTION OF A 14-STORY RESIDENTIAL BUILDING (199 UNITS) W/ NO BASEMENT TO INCLUDE PARKING ON LEVEL 1 (42 AUTO PARKING SPACES + 199 BIKE PARKING SPACES) AND ASSOCIATE SITE WORK AS PER PLANS. FULL BUILDING UNDER 101073356. (OCCUPANCY CLASSIFICATION: R-2, M / CONSTRUCTION CLASSIFICATION: 1A) CONSULTANT REVIEWER: GLOBETROTTERS ENGINEERING · 2026-03-23
TOWER CRANE PERMIT FOR FOUNDATION - FREESTANDING OPERATION OF A POTAIN MR418 TOWER CRANE PER PLANS. · 2026-03-12