Permits at 1410 S MUSEUM CAMPUS DR
25 permits on file · Chicago, IL · from the official municipal record
PERMIT EXPIRES ON 11/14/2026 ERECTION STARTS: 9/28/2026, ERECTION ENDS: 9/28/2026. CBC 2019. REINSTATEMENT OF 2024 PERMIT 101058268 FOR THE SEPT 28, 2026 MOBILE STAGE FOR THE CHICAGO BEARS AT STADIUM GREEN. SAME 1 - 24X20 SL100 WITH WINGS. FROST CHICAGO LIGHTING CO. WITH SOUND WORKS PRODUCTION INC. · 2026-09-14
PERMIT EXPIRES ON 11/09/2026 ERECTION STARTS: 9/25/2026, ERECTION ENDS: 9/26/2026. CBC2019 REINSTATEMENT OF 2022 PERMIT 100988694 FOR THE 2026 AIDS RUN STAGE AT STADIUM GREEN IN SOLDIER FIELD ON SEPT 26, 2026. SAME 1-24X20 SL-100 MOBILE STAGE WITH WINGS. CHICAGO SPECIAL EVENTS MANAGEMENT. · 2026-09-09
PERMIT EXPIRES ON 11/04/2026 ERECTION STARTS: 9/20/2026, ERECTION ENDS: 9/20/2026. CBC 2019. REINSTATEMENT OF 2024 PERMIT 101058268 FOR THE SEPT 20, 2026 MOBILE STAGE FOR THE CHICAGO BEARS AT STADIUM GREEN ON SEPT 20, 2026. SET-UP SEPT 20 AND TAKEDOWN SEPT 20, 2026. SAME 1 - 24X20 SL100 WITH WINGS. FROST CHICAGO LIGHTING CO. WITH SOUND WORKS PRODUCTION INC. · 2026-09-04
PERMIT EXPIRES ON 11/02/2026 ERECTION STARTS: 8/31/2026, ERECTION ENDS: 9/4/2026. SELF-CERT - CBC 2019 - PEER REVIEW. ERECTION OF TEMPORARY STAGE FOR A YE CONCERT AT SOLDIER FIELD, EVENT DATES SEPTEMBER 3RD-4TH, 2026 OVERALL AREA: 9,486 SQ.FT., INCLUDING:1.) CIRCULUR HALF DOME MAIN STAGE: 7,854 SF2.) BAND RISER: 24FT X 36FT X 36IN=864 SF3.) AUDIO SCAFFOLD SUPPORTS: 8FT X 8FT X 6FT= 64SF X 12 = 768 SF · 2026-09-02
PERMIT EXPIRES ON 10/27/2026 ERECTION STARTS: 9/17/2026, ERECTION ENDS: 9/18/2026. CBC 2019. AHA HEART WALK 2026 MOBILE STAGE AT SOLDIER FIELD SOUTH LOT ON SEPT 18, 2026. SETUP SEPT 17 AND TAKEDOWN SEPT 18, 2026. 1-24X20 MOBILE STAGE. RAVENSWOOD EVENTS WITH HRP CHICAGO. · 2026-08-27
PERMIT EXPIRES ON 10/25/2026 ERECTION STARTS: 8/23/2026, ERECTION ENDS: 8/30/2026. ERECTION STARTS: 8/23/2026, ERECTION ENDS: 8/30/2026. ARENA- BTS WORLD TOUR - SOLDIER FIELDTENT- 2 DAY EVENT, AUGUST 27-28, 2026ERECT ONE (1) 41.25X230 (12.5MX70M) STRUCTURE TENTSETUP 8/23/2026- REMOVE 8/30/2026ASSEMBLY · 2026-08-25
PERMIT EXPIRES ON 10/20/2026 ERECTION STARTS: 8/23/2026, ERECTION ENDS: 8/29/2026. SELF-CERT - CBC 2019 - PEER REVIEW. ERECTION OF TEMPORARY STAGE FOR A BTS CONCERT AT SOLDIER FIELD, EVENT DATES AUGUST 27TH & 28TH, 2026 OVERALL AREA: 21,130 SQ.FT., INCLUDING:1.) CIRCULAR MAIN STAGE: 10,482 SF2.) RUNWAY STAGE: 2,662 SF X 4= 10,648 SF · 2026-08-20
PERMIT EXPIRES ON 10/18/2026 ERECTION STARTS: 8/17/2026, ERECTION ENDS: 8/23/2026. SELF-CERT - CBC 2019 - PEER REVIEW. ERECTION OF TEMPORARY STAGE FOR THE R&B TOUR CONCERT AT SOLDIER FIELD, EVENT DATES AUGUST 21ST & 22ND, 2026 OVERALL AREA: 26,465 SQ.FT., INCLUDING:1.) MAIN STAGE: 11,800 SF2.) ARM STAGE: 1,348 X 2 =2,696 SF3.) T-SHAPED THRUST STAGE: 1,477 SF4.) ARROW SHAPED B-STAGE: 1,376 SF5.) DJ DELAY STAGE: 1,060 X 2 = 2,120 SF6.) VIP STAGE: 4,244 SF7.) FRONT OF HOUSE (FOH) MIX HUT: 24FT X · 2026-08-19
REINSTATE PERMIT NO 101071977 MUST BEGIN WORK AND OR REQUEST INSPECTION NO LATER THAN ***DECEMBER 2026*** ON PERMIT NO 101071977 · 2026-08-19
PERMIT EXPIRES ON 10/14/2026 ERECTION STARTS: 8/30/2026, ERECTION ENDS: 8/30/2026. CBC 2019 - 2026 BLACK ON THE BLOCK STAGE AT STADIUM GREEN ON AUG 30, 2026. SETUP AND TAKEDOWN ARE AUG 30. 1-24X20 SL-100 MOBILE STAGE WITH WINGS. SOUND WORKS PRODUCTION INC. · 2026-08-14
ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: ASSEMBLY. START DATE: 8/31/2026. END DATE: 9/30/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND MAKE THOSE RECORDS AVAILABLE TO THE BUILDING COMMISSIONER UPON REQUEST. · 2026-08-10
ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: ASSEMBLY. START DATE: 8/17/2026. END DATE: 9/16/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND MAKE THOSE RECORDS AVAILABLE TO THE BUILDING COMMISSIONER UPON REQUEST. · 2026-08-10
ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: ASSEMBLY. START DATE: 8/24/2026. END DATE: 9/23/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND MAKE THOSE RECORDS AVAILABLE TO THE BUILDING COMMISSIONER UPON REQUEST. · 2026-08-10
PERMIT EXPIRES ON 10/05/2026 ERECTION STARTS: 08/03/2026, ERECTION ENDS: 08/09/2026. SELF-CERT - CBC 2019 - PEER REVIEW. ERECTION OF TEMPORARY STAGE FOR A FOO FIGHTERS CONCERT AT SOLDIER FIELD, EVENT DATES AUGUST 8TH 2026 OVERALL AREA: 20,788 SQ.FT., INCLUDING:1.) MAIN STAGE: 88FT X 184FT = 16,192 SF2.) RUNWAY STAGE: 8FT X 40FT= 320 SF3.) B-STAGE: 20FT X 20FT=400 SF4.) FRONT OF HOUSE (FOH) MIX HUT: 24FT X 32FT = 768 SF5.) 83FT TALL DELAY TOWERS: 37FT X 21FT = 777 X 4 = 3,108 SF · 2026-08-05
PERMIT EXPIRES ON 09/24/2026 ERECTION STARTS: 7/18/2026, ERECTION ENDS: 7/26/2026. SELF-CERT - CBC 2019 - PEER REVIEW. ERECTION OF TEMPORARY STAGE FOR A KAROL G CONCERT AT SOLDIER FIELD, EVENT DATES JULY 24TH & 25TH 2026 OVERALL AREA: 20,143 SQ.FT., INCLUDING:1.) MAIN STAGE: 9,344 SF2.) TRIANGULAR APRON STAGE: 3,472 SF3.) U-SHAPED THRUST STAGE: 3,619 SF4.) RUNWAY STAGE: 732 SF5.) FRONT OF HOUSE (FOH) MIX HUT: 24FT X 24FT = 576 SF6.) VIP RISER: 20FT X 24FT=480 SF7.) 71FT TALL DELAY TOWERS: 20 · 2026-07-24
ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: ASSEMBLY. START DATE: 8/3/2026. END DATE: 9/2/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND MAKE THOSE RECORDS AVAILABLE TO THE BUILDING COMMISSIONER UPON REQUEST. · 2026-07-23
ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: ASSEMBLY. START DATE: 7/14/2026. END DATE: 1/10/2027. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND MAKE THOSE RECORDS AVAILABLE TO THE BUILDING COMMISSIONER UPON REQUEST. · 2026-07-14
ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: ASSEMBLY. START DATE: 7/24/2026. END DATE: 8/23/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND MAKE THOSE RECORDS AVAILABLE TO THE BUILDING COMMISSIONER UPON REQUEST. · 2026-06-30
PERMIT EXPIRES ON 08/24/2026 ERECTION STARTS: 6/22/2026, ERECTION ENDS: 6/28/2026. SELF-CERT - CBC 2019 - PEER REVIEW. ERECTION OF TEMPORARY STAGE FOR AN ED SHEERAN CONCERT AT SOLDIER FIELD, EVENT DATES JUNE 27TH, 2026 OVERALL AREA: 8,837 SQ.FT., INCLUDING:1.) MAIN STAGE: 5,659 SF2.) FRONT OF HOUSE (FOH) MIX HUT: 20FT X 17FT = 340 X 2=680 SF3.) B-STAGE: 20FT DIA. CIRCLE = 314 SF4.) 69FT TALL DELAY TOWERS: 21FT X 26FT = 546 X 4 = 2,084 SF · 2026-06-24
ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: ASSEMBLY. START DATE: 6/17/2026. END DATE: 7/17/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND MAKE THOSE RECORDS AVAILABLE TO THE BUILDING COMMISSIONER UPON REQUEST. · 2026-06-22
ELECTRICAL MAINTENANCE PERMIT. OCCUPANCY: ASSEMBLY. START DATE: 6/23/2026. END DATE: 7/23/2026. ALL WORK UNDER THIS PERMIT MUST BE PERFORMED BY EMPLOYEES OF THE LISTED ELECTRICAL CONTRACTOR. THE ELECTRICAL CONTRACTOR MUST MAINTAIN COMPLETE WRITTEN RECORDS OF ALL WORK PERFORMED UNDER THIS PERMIT AND MAKE THOSE RECORDS AVAILABLE TO THE BUILDING COMMISSIONER UPON REQUEST. · 2026-06-22
PERMIT EXPIRES ON 08/08/2026 ERECTION STARTS: 6/15/2026, ERECTION ENDS: 6/21/2026. SELF-CERT - CBC 2019 - PEER REVIEW. ERECTION OF TEMPORARY STAGE FOR A MORGAN WALLEN CONCERT AT SOLDIER FIELD, EVENT DATES JUNE 19TH & 20TH, 2026 OVERALL AREA: 17,723 SQ.FT., INCLUDING:1.) MAIN STAGE: 11,217 SF2.) AIRPLANE SHAPED THRUST STAGE: 2,900 SF2.) FRONT OF HOUSE (FOH) MIX HUT: 726 SF3.) C-STAGE: 672 SF3.) 63FT TALL DELAY TOWERS: 552 SF X 4 = 2,208 SF · 2026-06-08
LINE VOLTAGE ELECTRICAL WORK. NEW PERMANENT 300 AMP SERVICE DISCONNECTING MEANS WITH 2 CIRCUITS. RECEPTACLE OUTLETS: 2 . LIGHTING OUTLETS: 0. SPECIFIC LOCATION: SOLDIER FIELD SOUTH LOT. · 2026-06-08
PERMIT EXPIRES ON 07/28/2026 TEMPORARY STRUCTURE (FIELD LEVEL ALUMINUM PLATFORMS ADDED TO FIELD LEVEL, EAST SIDELINE). NOTE THAT SINCE THIS IS THE 6TH YEAR, THE ORIGINAL PERMIT ISSUED FROM 2020 (100980322) NO LONGER CAN BE REINSTATED. ERECT 08/01/2026 REMOVAL 01/26/2027 · 2026-05-28
LINE VOLTAGE ELECTRICAL WORK. NEW PERMANENT 200 AMP SERVICE DISCONNECTING MEANS WITH 2 CIRCUITS. RECEPTACLE OUTLETS: 2 . LIGHTING OUTLETS: 0. SPECIFIC LOCATION: SOUTH PARKING LOT. · 2026-05-28
Monitoring a permit at this address?